John Cooper, Pete Hellier and Wayne Starsmore. Took in 4 bags of sand and some
additional cement. Three mixes added to the Spiral Staircase. No cement left
and only 1 bag of sand. 1¾ hours.
Survey
Saturday 27th June 2020
John Cooper, Mark Easterling (Bean) and Wayne Starsmore. Took in 2 bags of sand. Three mixes added to Spiral Staircase, nearly finished. Only a half bag and sand and 1-2 mixes of cement left now. Bottom section of ladder removed and brought out. Bean took a look at the bottom but agrees cementing required before going down any further. 1½ hours.
Tuesday 23rd June 2020
John Cooper and Wayne Starsmore. First trip for 3 months (Covid lockdown) so a cementing the Spiral Staircase trip. Four mixes added, just need to level things off now. Only 2 bags of sand left. 1½ hours.