Spider Hole November 2021

Monday 23rd January 2017

James Collings, John Cooper, Vern Freeman, Simon Richards (Nik-Nak), Adrian Vanderplank and Jude Vanderplank. 36 loads hauled up Four Tonne shaft before Adrian said there was no more spoil. John then joined him and he charged the holes drilled weekend before last and more spoil was created. 2¼ hours. John.

John Cooper, James Collings, NikNak, Vern Freeman, Jude Vanderplank & Myself. A final clearing of the bottom of 4 tonne shaft. 36 buckets removed and now we the empty bottom!!! John Cooper & Myself then to load the holes drilled on the 14.01/2017. All 4 holes loaded with 40gm cord and connected with 12gm cord. The firing wire now only just reaches the ledge. The charge was fired and we made our way out. John as usual climbed the ladders. By the time I was ready to S.R.T. out the fumes were in the bottom chamber. Quite encouraging really. I think that proves we have the draught back and possibly it means we are digging in the right direction. Adrian.

Sketch by Adrian Vanderplank.