Monday 23rd May 2016

John Cooper and Adrian Vanderplank. Ladder for bottom pitch (11.4m) taken in and through bolt inserted with hanger. Two long holes and one short one drilled at bottom (rather drippy this evening!) ready for bang. Hanger for ladder up to spoil dump above Four-Tonne Shaft moved up wall a couple of metres. 2 hours. John.

John Cooper & Myself. Armed with drill, ladder & hangers down to the bottom. One hanger installed for the bottom ladder and ladder attached. 3 x 10mm holes x 500mm drilled in stal & rock bulge ready for removal later. Magic smoke squirted into a gap at floor level on the North side showed a detectable draught (Whoo hoo). Back to the top shafts and the ladder up to the spoil dumping site was raised another 1.5 meters. Good working session. Adrian.